National Grid system operator separation and transaction records

Sources checked

From separation decision to the reported sale proceedsNational Grid system operator separation and transaction records
  1. April 2022
    Independent operator decision

    Government and Ofgem agree to proceed Source 1

  2. October 2023
    Enabling legislation passed

    Energy Act provides the framework for separation Source 2

  3. 13 September 2024
    Designation decision published

    Electricity licence conversion and a new gas planning licence Source 3

  4. 13 September 2024
    Initial enterprise value announced

    £630 million, subject to completion adjustments Source 4

  5. 1 October 2024
    Disposal completes and NESO starts

    National Grid system operator moves into public ownership Source 2

  6. 2024/25 annual results
    Total consideration and gain reported

    £673 million consideration and £187 million disposal gain Source 2

Licence changes, completion and the accounting of proceeds were distinct events.

Source 1 Source 2 Source 3 Source 4

National Grid system operator separation and transaction records

Enterprise value, total consideration, cash proceeds net of cash disposed and disposal gain are different measures. The dates show where each was reported.

6 records
Source
April 2022Independent operator decisionGovernment and Ofgem agree to proceedSource 1
October 2023Enabling legislation passedEnergy Act provides the framework for separationSource 2
13 September 2024Designation decision publishedElectricity licence conversion and a new gas planning licenceSource 3
13 September 2024Initial enterprise value announced£630 million, subject to completion adjustmentsSource 4
1 October 2024Disposal completes and NESO startsNational Grid system operator moves into public ownershipSource 2
2024/25 annual resultsTotal consideration and gain reported£673 million consideration and £187 million disposal gainSource 2

Source links